I’m facing a case that I cannot add task with 100% progress (completed task) with PSI programmatically.
I need to import/sync tasks from another system to Project Server. The task include some custom fields. There is no problem, if I add tasks when the property %complete is less then 100% (not complete). But if there is a task with 100% complete exist, after do QueuePublish method at the end, nothing has changed to the project. All tasks have not added to the project.
After a few hours trial-and-error, I still cannot found the solution.
Then I do some cheating flow, that I add/insert the task directly to the database. Of course Microsoft not recommend this way. But it works for me.
Some property and value that I have to inject manually to database (table Draft and Published) :
- Task_Pct_Comp : 100
- Task_Pct_Work_Comp : 100
- Task_Act_Finish, equals to Task_Finish_Date
- Task_Stop_Date, equals to Task_finish_Date
- Task_Act_Dur, equals to Task_Dur
That’s it.. When opening project in Project Center, I can see the task has completed with thick mark at the left column 😉